Halden Tower: 32 storeys on a zero-laydown site

A 640,000 sq ft office and retail tower rising over the Chicago Loop on a site boxed in by the L and two live streets. The structure topped out two weeks early and the curtain wall is now closing in levels 22–32.

Client: Halden & Co. Duration: 30 months Year: 2027
The challenge

No room to stage, no room to slip.

Halden & Co. bought a corner lot in the Loop with the L tracks running along one side and two arterial streets on the others. Every beam, panel and pour had to arrive just in time — and anchor tenants had signed leases tied to a fixed occupancy date.

  • 0 sq ftof on-site laydown space
  • 14anchor-tenant floors pre-leased
  • $1.1Mper month in lease penalties if late

The first scheme called for a cast-in-place concrete frame, which would have needed a second tower crane the site simply could not hold. Halden needed a builder that could re-plan the structure, sequence deliveries by the hour and still commit to a guaranteed maximum price before the design was complete.

We joined at schematic design, signed a $214M GMP at 60% drawings and took responsibility for city coordination with the transit authority and the Department of Transportation.

Our solution

One crane, one clock.

We reorganized the job around a single tower crane and an off-site marshalling yard, with deliveries booked in 30-minute windows through a shared logistics app.

  1. 01

    Switch the frame

    A composite steel frame with a concrete core cut the crane picks per floor by 40% and let us build a floor every four working days.

  2. 02

    Stage off site

    A leased yard six miles south held steel, curtain-wall units and MEP racks, released to site only when the hook was free.

  3. 03

    Close in early

    Unitized curtain-wall panels went on three floors behind the steel, so interior trades started on level 4 while steel was still rising on level 20.

The results

Topped out, two weeks early.

Progress as of the latest monthly owner report, measured against the master schedule attached to the GMP.

64 % Work in place

Curtain wall now closing in levels 22–32.

2 wks Ahead at topping out

Structure finished before the winter shutdown.

4 days Per typical floor

From composite steel and a single crane cycle.

0 Lost-time incidents

Across 1.3M craft hours worked to date.

“We gave Corwell a corner lot with no staging space and tenants waiting on a date. They redesigned the frame, ran the site like an airport and have not missed a milestone yet. We are already talking about the next tower.”
Marcus Hale Head of Development, Halden & Co.