Kestrel Energy: 410,000 sq ft in 14 months

A 410,000 sq ft parts and equipment hub for a utility serving three states, with a storm-season deadline. We designed, permitted and built it in 14 months — and handed it over three weeks early.

Client: Kestrel Energy Duration: 14 months Year: 2025
The challenge

Storm season doesn’t wait.

Kestrel Energy needed one hub to stock transformers, poles and line hardware for crews across Ohio, Indiana and Kentucky. Its old warehouses were scattered across five leased buildings, and the new one had to be live before the spring storm season.

  • 14 mofrom first sketch to first truck out
  • 5leased warehouses to consolidate
  • 60 theaviest transformer on the racking plan

Design-bid-build would have taken 22 months and pushed opening past two storm seasons. Kestrel needed one team that could design a heavy-load slab, buy long-lead equipment before the drawings were final and still guarantee the price.

We signed a progressive design-build contract, fixed the GMP at 50% design and ran design, procurement and construction in parallel with weekly owner reviews.

Our solution

Three moves, one contract.

The schedule was built backward from the storm-season date, with every long-lead item bought before it reached the critical path.

  1. 01

    Design for the load

    A 10-inch post-tensioned slab with heavy-haul aprons carried 60-ton transformers without the deep footings of the original concept.

  2. 02

    Buy early

    Structural steel, two 40-ton bridge cranes and 48 dock doors were ordered at 30% design, locking prices before the steel market moved.

  3. 03

    Build in parallel

    Tilt-up panels were cast on the slab while the roof went on behind them, with two self-perform crews working in opposite directions.

The results

Fourteen months, first truck out.

Measured against the GMP and master schedule agreed at contract — and confirmed in Kestrel’s own close-out audit.

3 wks Ahead of schedule

Crews were dispatched from the hub before the first April storm.

68 % Work self-performed

Concrete, tilt-up, steel and site civil by our own crews.

$2.4 M Returned to the owner

Unused contingency and buyout savings under the GMP.

0 Lost-time incidents

Across 410,000 craft hours on site.

“Corwell treated our storm-season date like their own. They ordered the cranes before the drawings were done, kept a 260-person site incident-free and handed over a building our crews used on day one.”
Rebecca Thornton VP, Supply Chain, Kestrel Energy